Traffic clearance issue at Chingrighata delays New Garia–airport Metro project to mid-2028

  • Full Metro connectivity between New Garia and the airport is now expected only by mid-2028
  • Traffic clearance issues at Chingrighata have stalled construction work for the past three months
  • Kolkata Metro GM said original mid-2027 deadline cannot be met due to approval delays

03 Feb 2026

Traffic clearance issue at Chingrighata delays New Garia–airport Metro project to mid-2028

The full launch of the Metro service connecting New Garia to Netaji Subhas Chandra Bose International Airport is set to be delayed further, with the project now expected to be completed only by mid-2028. The delay has been attributed to the lack of traffic clearance in the Chingrighata area.

Kolkata Metro General Manager Subhranshu Shekhar Mishra shared the update on Monday, following the Railway Minister’s budget press conference. He said the project was originally targeted for completion by mid-2027 but has faced hurdles over the past three months.

According to Mishra, construction work at Chingrighata has remained stalled due to the absence of necessary approvals from the traffic department. This has significantly slowed down progress on a key stretch of the corridor.

He added that even if traffic clearance is granted immediately, it would still take until mid-2028 to complete the entire New Garia–airport Metro project and make it fully operational.

Ad Image
Comments

No comments to show. Log in to add some!

Other Relevant Stories


Traffic clearance issue at Chingrighata delays New Garia–air
Full Metro connectivity between New Garia and the airport is now expected only by mid-2028 Traffic clearance issues at Chingrighata have stalled construction wo





Download The Taaza Tv App Now to Stay Updated on the Latest News!


play store download
app store download
app img


Breaking News